UK Explained
Transport · Trains

How often do trains run on time?

84.4% of passenger trains in Great Britain arrived on time over the 13 four-week periods to August 2026. The average passenger arrived 3.4 minutes late, and 5.4% of planned trains were cancelled in the latest four-week period.

TRAINS ON TIME
84.4%

Moving annual average to August 2026. down 0.7 points on July 2026.

PASSENGER LATENESS
3.4

Minutes late, average passenger, year to August 2026.

CANCELLED
5.4%

Of planned trains, latest four weeks to August 2026.

Punctuality over time

TRAINS ON TIME (PUBLIC PERFORMANCE MEASURE)
84.4%
▼ 7.6 points since January 2021
What’s this?

The share of passenger trains in Great Britain that arrived at their final stop on time, defined as within 5 minutes (10 for long-distance services), over the latest 13 four-week periods.

What it cannot tell you: A cancelled train counts as late, but a train that is on time at the end can still have been late at stations on the way. It counts trains, not passengers, so a busy train counts the same as an empty one.

Source: Office of Rail and Road, passenger rail performance · latest August 2026
CSV
AVERAGE PASSENGER LATENESS
3.4 min
▲ 1.6 min since January 2021
What’s this?

The average number of minutes late that a passenger arrives, counting trains that run to time as zero, over the latest 13 four-week periods.

What it cannot tell you: It is an average across all passengers, so a few very late journeys are hidden by many on-time ones.

Source: Office of Rail and Road, passenger rail performance · latest August 2026
CSV
TRAINS CANCELLED
5.4%
▲ 2.8 points since January 2021
What’s this?

The share of planned passenger trains in Great Britain that were cancelled in each four-week period, counting a part-cancelled train as a fraction.

What it cannot tell you: Strikes, storms and engineering work push up cancellations in some periods. It counts trains, not passengers affected.

Source: Office of Rail and Road, passenger rail performance · latest August 2026
CSV

Period by period

Great Britain, moving annual averages.

PeriodTrains on time (public performance measure)Average passenger lateness
August 202684.4%3.4
July 202684.8%3.3
June 202685.0%3.3
May 202685.2%3.2
April 202685.5%3.1
March 202685.5%3.1
February 202685.6%3.1
January 202685.6%3.1
December 202585.5%3.1
November 202585.4%3.1
October 202585.2%3.2
September 202585.2%3.2
What it cannot tell you. A cancelled train counts as late, but a train that is on time at the end can still have been late at stations on the way. It counts trains, not passengers, so a busy train counts the same as an empty one. The measure counts trains, not passengers, so a busy train counts the same as an empty one, and a train that is on time at the end can still have been late on the way.

Questions people ask

What counts as on time?

A train is on time if it arrives at its final stop within 5 minutes of the planned time (10 minutes for long-distance trains). A cancelled train counts as not on time. This is called the public performance measure.

Does this include Scotland and Wales?

It covers all of Great Britain: England, Scotland and Wales. Northern Ireland's railways are separate.

Why use a moving annual average?

Single four-week periods swing with weather, strikes and engineering work. The annual average over the latest 13 periods smooths those swings so the trend is easier to see.

What does “trains on time (public performance measure)” measure?

The share of passenger trains in Great Britain that arrived at their final stop on time, defined as within 5 minutes (10 for long-distance services), over the latest 13 four-week periods. It was 84.4% (% of trains, moving annual average) in August 2026, down 7.6 points on January 2021. The highest we have is 93.4% (March 2021) and the lowest 84.4% (August 2026).

What does “average passenger lateness” measure?

The average number of minutes late that a passenger arrives, counting trains that run to time as zero, over the latest 13 four-week periods. It was 3.4 (minutes late, moving annual average) in August 2026, up 94% on January 2021. The highest we have is 3.4 (August 2026) and the lowest 1.4 (March 2021).

What does “trains cancelled” measure?

The share of planned passenger trains in Great Britain that were cancelled in each four-week period, counting a part-cancelled train as a fraction. It was 5.4% (% of planned trains (four-week periods)) in August 2026, up 2.8 points on January 2021. The highest we have is 8.0% (December 2022) and the lowest 0.9% (April 2020).

Sources: Office of Rail and Road, passenger rail performance. Updated every night. Each chart has a CSV and a Share button.

See also: Train and bus fares · Road deaths